Visionary power. Wherever you want.
Please choose language

New traction chain for lasting performance.

The project began with a bold objective: Upgrade an aging hydropower plant, originally commissioned in the 1960s, to a modern facility capable of high efficiency and reliability for decades to come. Instead of a partial overhaul, our customer requested a completely new traction chain, including wicket gate and turbine shaft - a departure from typical revitalizations where components are often only refurbished. 

In addition, the goal was to upgrade the existing machine - enabling faster start and stop sequences and quicker response to load changes. This capability is increasingly essential for power grids with a high share of wind and solar generation, where flexibility and reaction speed are key to maintaining stability. Along with these improvements, hydraulic optimizations increased the turbine’s efficiency by around 3% at nominal discharge, resulting in higher power output and improved overall performance. Together, these measures transformed the unit into a modern, high-performance system ready to meet the demands of today’s dynamic energy landscape.

Facts at a glance

3D site measurement:

Building the
foundation for accuracy.

Achieving the ultra-tight tolerances required for this revitalization began long before installation. With few original drawings available, a Global Hydro specialist was on site to carry out extensive 3D measurements and photo documentation, capturing all critical dimensions of the existing structure. Using a Laser Tracker with sub-0.01 mm accuracy and more than 500 measuring points, all critical dimensions of the existing structure were captured and temperature-compensated in a central coordinate system. This data made it possible to position the newly manufactured wicket gate ring precisely relative to the existing lower ring, to machine the guide vane bores on site with pinpoint accuracy, and to adjust the length of each individual guide vane for a perfect fit. Even the discharge ring was measured to enable the new runner to be machined for optimal clearances.

Precision at its finest:

Advanced line boring process.

A defining feature of this revitalization project is the advanced on-site line boring process carried out directly in the powerhouse. Since the original turbine design has the lower wicket gate ring permanently embedded in concrete, removal or replacement was not an option. Therefore, a mobile machining center was installed directly on the new upper wicket gate ring. From this precisely aligned reference point, the lower guide vane bushings were bored with sub-millimeter accuracy. This method allowed the new guide vanes to be matched perfectly to the existing lower wicket gate ring and ensured that every bearing bore sat exactly in the designed position. Achieving this level of alignment was essential to maintain an exceptionally small guide vane clearance and ensure smooth operation.

By performing the machining on site, Global Hydro avoided time-consuming civil works and achieved a seamless fit between new and existing components. This approach reflects Global Hydro’s commitment to precision, adaptability and continuous innovation in hydropower modernization.

Tailored engineering solutions.

The revitalization demanded more than precision machining. Several unique conditions required custom-engineered approaches, each highlighting Global Hydro’s ability to adapt designs and methods to even the most challenging environments.



Hydraulics upgrade

The oil-hydraulic system was converted from low-pressure (10 bar) to modern high-pressure (100 bar) standards, enabling more compact, efficient components and faster response to load changes.



Environmental improvements

Another key requirement from the customer was to minimize environmental risks from oil and grease entering the water. The old runner, previously filled with pressurized oil, was replaced by a design using only biodegradable lubricant. In addition, the existing wicket gate bushes - originally grease-lubricated - were exchanged for grease-free bearings, eliminating the need for any water-side lubrication.



Turbine bearing redesign

Because no reverse-axial bearing is located on the generator side, the main turbine bearing was engineered to handle both radial and axial loads. The long tailrace tunnel at this site also required countermeasures to manage potential reverse axial thrust during load rejection. This integrated design resulted in a larger bearing size, which in turn limited accessibility to the seals and necessitated a new drainage concept.



Seal replacement from below

Due to the enlarged bearing, seals on the runner side were replaced from underneath - an unconventional but effective approach.



Split upper wicket gate ring

Limited space and fixed concrete structures necessitated a two-part upper wicket gate ring for assembly through a narrow opening.

Pre-assembly and factory acceptance testing in Austria.

Before transport to site, the traction chain was pre-assembled to the highest possible degree at our Austrian Innovation and Manufacturing Center. This extensive preparation ensured that all interfaces and tolerances were validated under workshop conditions, reducing complexity and risk during installation on site.

A separate in-house factory acceptance test allowed the customer to witness pressure tests and assembly quality first-hand. Their satisfaction during the FAT confirmed that the assembled components fully met the stringent quality and testing standards set by Global Hydro.


Logistics without compromise.

Given the scale of the components - the traction chain alone measuring 6.7 x 3.0 x 3.3 m - transport had to be carefully planned. All parts were shipped via truck and ferry, with the traction chain requiring special handling due to its size. Nevertheless, delivery to site took just approximately one week, keeping the overall project timeline on track.

This project is more than a modernization - it is a statement of what’s possible when engineering excellence meets innovation. By combining precision processes like on-site line boring with custom-tailored solutions and state-of-the-art manufacturing. Global Hydro sets new benchmarks for revitalizing complex hydropower assets worldwide.
Heinz-Peter Knass, CEO

Engineering under tight tolerances.

Revitalizing a decades-old hydropower plant required an exceptional level of precision from the very start. With only limited documentation available and extremely tight tolerances to meet, every detail had to be carefully planned and executed.

Tailored design ensuring a perfect fit.

Global Hydro responded with a fully integrated approach. Every interface was surveyed, components were designed and pre-assembled to the highest tolerances at our Innovation and Manufacturing Center in Austria, and advanced on-site line boring aligned new and existing parts directly in the powerhouse.

Maximum performance and long-term reliability.

The result is a revitalized plant that delivers higher efficiency, greater operational flexibility and extended service life. By uniting engineering, manufacturing and installation into one coordinated process, Global Hydro ensures that even the most challenging sites become high-performing, future-proof renewable energy assets.

Ready to modernize your hydropower assets?

Every project has its own challenges and goals. Contact our experts to discuss your requirements - Global Hydro develops tailored revitalization solutions to meet your specific needs.

Contact Person

Roland Fleischmann

Senior Sales Manager Revitalization

+43 (7285) 514 0055

Contact

Curious about more?