Visionary power. Wherever you want.
Please choose language

In-house development: 
Completely new turbine concept.

 
Combining vertical Kaplan spiral and horizontal pit turbine principles.

The technological centerpiece of Stegenwald is a turbine concept that was completely redeveloped specifically for this project. It combines the principles of a vertical Kaplan spiral turbine with those of a horizontal pit turbine in a compact layout tailored to the site conditions. Global Hydro has previous experience with pit turbines, and this knowledge was directly incorporated into the Stegenwald solution, reducing technical risk despite the novelty of the configuration.

Instead of admitting water directly from the front, the flow is guided from above through an inlet ramp and a specially shaped intake spiral. The generator and gearbox are positioned in front of the turbine rather than on top of it, which is the usual arrangement for similar plants. The design target was to find the best possible compromise between a vertical spiral turbine and a horizontal pit turbine in terms of efficiency, structural integration and cost. The result is a layout that delivers a higher efficiency by approximately 1 to 1.5 percentage points compared to conventional solutions, a significant gain over the lifetime of the plant.

Elimination of a weir field.

Improving flood handling.
By combining the features of a vertical spiral turbine with those of a horizontal pit turbine, the design team was able to avoid the need for a third weir field at Stegenwald. The plant layout uses:

  • Two weir fields with radial gates
  • Two flap gates installed downstream of the turbine inlet area

In flood events, not only the two weir fields but also the flap gates can be operated to discharge high flows. This means that the plant can pass more water during flood conditions than would have been possible with a conventional layout that relied on an additional weir field.

This concept makes the plant more flexible in operation, optimizes costs on the civil side and increases safety and robustness during extreme hydrological events.

Simulation driven design.

Through development partnerships.
The turbine concept and its hydraulic geometry were developed in close cooperation with technical universities. The process included:

  • Initial CAD based design of the hydraulic components
  • Extensive CFD analyses to refine the intake, spiral and runner geometry
  • Optimization of the turbine efficiency and flow guidance

The turbine was designed to withstand temperature dependent and load dependent deformations. Special attention was given to the load paths and the axial bearing arrangement. The axial bearing, located in the gearbox, was moved to the front side and integrated into a conical housing so that forces are kept locally where they arise. This optimized load introduction concept reduces structural stresses and contributes to long term reliability.

Sediment
management.

Engineered for hydraulic resilience.
The Salzach carries significant bed load, which makes sediment management a key design factor. The turbines and the hydraulic design were therefore optimized with sediment passage in mind.

Key measures include:

  • A gravel edge to reduce the influx of coarse material into the turbine area
  • An inlet ramp that guides both water and bed load centrally, as confirmed by CFD analyses
  • High flow velocities in the spirals to ensure that sediment is transported through the turbines and does not settle
  • Flushing lines at the lowest points to remove accumulated material

These hydraulic and structural measures help maintain turbine performance over time, reduce abrasion related damage and support stable plant operation during varying sediment loads.

We had to carefully plan how to position, align and install every component. To manage load and temperature-induced deformation, we optimized force transmission by relocating the axial bearing to the front and designing a conical housing to keep forces local.

Christian Witti, Team Leader Engineering Kaplan

From concept to commissioning in just 2.5 years.

Stegenwald is a run-of-river hydropower plant on the Salzach River in Austria. It was designed to combine high efficiency, operational flexibility and a compact layout tailored to the specific site conditions.

From a project delivery perspective, this hydropower plant is equally remarkable. After a lengthy preparation and permitting phase of more than 10 years, the actual construction and implementation were completed in only about 2.5 years, from the start of civil works in early 2023 to commissioning in the second quarter of 2025.

Facts at a glance

Turn-key Solution from our Austrian Innovation and Manufacturing Center.

Full scope delivery with pre-assembly that pays off

From initial concept to grid connection: We delivered the entire electromechanical package - seamlessly planned, manufactured, tested and installed. Thanks to our high degree of pre-assembly and integrated engineering approach, we ensured maximum quality with minimal site risk.

learn more
Seamless logistics and transport execution

Even with limited access, tight spaces and strict transport constraints, Global Hydro ensured flawless delivery and on-site handling of all components. With intelligent planning, modular pre-assembly and just-in-time delivery, we kept the project on track – and reduced time, cost and complexity.

learn more
On-site installation and commissioning

Precision planning, smart pre-assembly and smooth commissioning: The turbine systems were installed and started up in record time. Thanks to our proven process and expert execution, the plant entered operation on schedule and above expectations - delivering smooth, reliable performance from day one.

learn more

Full scope delivery with pre-assembly that pays off.

Complete electromechanical package.

Global Hydro delivered and implemented the entire electromechanical scope for Stegenwald, including turbines, generators, gearboxes, cooling units, lubrication and hydraulic units as well as all turbine related steel structures and auxiliary systems.

The project was divided into two main lots:

  1.  Design and engineering
  2.  Manufacturing, delivery, installation and commissioning

Global Hydro handled all relevant designs in an integrated way, covering mechanical, hydraulic and structural aspects on the machine side and in close coordination with the civil works. This holistic approach ensured that all system interfaces were controlled and that the technical solution was coherent from initial concept to final operation.
 

Design, pre-assembly and testing.

In Global Hydro’s Innovation and Manufacturing Hub in Austria, the components were manufactured and pre-assembled in functional groups. The process followed a clear strategy:

  • Create the highest possible degree of pre-assembly
  • Carry out functional tests and adjustments in the factory
  • Reduce installation time on-site

By transferring as much work as possible into the controlled factory environment, Global Hydro ensured high quality and minimized on-site risks and delays.

01
Wicket Gate

The wicket gate was fully assembled with its half shells, adjusted and then disassembled again for transport. This saved significant time during installation on-site, especially given the constraints of the site bridge and a tight railway underpass.

02
Runner

The runner, with an outer diameter of 3.6 m and maintenance friendly external runner adjustment, was statically balanced. Functional testing also included: 

  • Runner adjustment and function tests
  • Pressure tests on the runner adjustment hydraulic system and cylinders
  • Verification of tightness and reliable movement
03
Traction Chain

The traction chain was pre-assembled, aligned and tested as a unit before being transported to the site.

Seamless logistics and transport
execution - even in demanding environments.

The transport of the main components to Stegenwald was a project in itself, with access only via narrow routes, a tight railway underpass and a temporary construction bridge limited to 85 tons. To stay within this limit, the individual delivery units, such as the wicket gate and the traction chain were designed so that their weight on the truck did not exceed 32 tons. All assemblies were predesigned, preassembled and then put into suitable transport units, ensuring that they remained roadworthy while still allowing efficient and technically robust reassembly on-site.

Before each special transport, route inspections and planning meetings were held. Mobile cranes were arranged in advance and positioned to allow direct lifting into the turbine shafts where possible, especially on the weir bridge. This minimized intermediate handling and further reduced time and risk during installation.

The project followed a just in time delivery philosophy. Colli were scheduled to arrive when needed to avoid congestion at the site, while civil works and mechanical installations progressed in parallel. Weekly coordination meetings involving all key stakeholders and Global Hydro’s project and site management teams ensured that short-term changes could be accommodated while keeping the overall schedule on track.

Transportation of the traction chain to the site.

Turbine installation on-site
in two major steps:

Precision, planning and experience were key to a smooth on-site assembly. Thanks to a high degree of factory pre-assembly and well-coordinated logistics, the installation of the turbine systems could be carried out in two clearly defined phases - efficiently, safely and on schedule.

01
Wicket gate and stay vane rings.

In summer 2024, the half shells and wicket gate assemblies were lifted into the turbine shafts. Wind conditions during this period were close to the operational limits for crane work, which required careful planning and monitoring. With component weights of around 30 tons per lift, two mobile cranes were used to install the turbine parts into the shaft. To avoid overloading the civil structures, crane positions on the weir bridge were defined and checked in advance.

The benefits of factory pre-assembly became clear at this stage. Because the components had already been fitted and adjusted at the manufacturing site, on-site assembly was faster and required less adjustment work, reducing blocking times on-site.

02
Traction chains, gearboxes, generators and auxiliaries.

In December 2024, both traction chains were installed. The pre-assembled units had been set up in the factory with the runner blades at 30 degrees and with no blade positioned at twelve o’clock, allowing the crane rail in the wicket gate to take over the runner during installation. Afterwards, gearboxes, generators and auxiliary units such as lubrication, cooling and hydraulic systems were installed and connected. All piping, auxiliary systems and instrumentation were then integrated and tested, preparing the units for commissioning.

Commissioning and operational experience.

A key milestone was reached in January 2025 when the first turbine shaft was flooded and the Salzach River was diverted through the new turbine. After the successful leak tests and checks, the second turbine followed in March 2025.

The commissioning sequence included:

1. Dry commissioning

  • Functional tests of auxiliary systems
  • Verification of control and protection systems

2. Wet commissioning

  • Flooding of the turbines
  • Bringing the machines to temperature with minimal water flow
  • Warm run at nominal speed without load to verify mechanical behavior

3. Grid synchronization and performance tests

  • Synchronization to the grid
  • Fine tuning of the control system
  • Differential pressure measurements and shutdown tests at various load levels

The plant entered trial operation in the second quarter of 2025 and was fully commissioned in line with the project schedule. Probationary operation for the second machine set was completed in mid-June, and for the first machine set by the end of July. Since then, both turbine units have been running in regular operation.

Feedback from the operator has been very positive. The turbines operate very smoothly and reliably, and the overall system’s performance exceeds expectations.

 

 

To avoid any delays on site, it was crucial that all machine components were delivered and installed on schedule. That’s why we focused on a just-in-time delivery approach - each part arrived exactly when it was needed."

Rainer Pühringer, Project Manager

A special project in every respects.

Stegenwald showcases a completely new turbine design that combines hydraulic, structural and operational advantages. The project has significantly expanded the know-how of everyone involved, particularly in the fields of combined spiral pit turbine design, complex logistics and high pre-assembly strategies. Stegenwald is a reference plant for both national and international customers who are looking for innovative hydropower solutions and state-of-the-art technology that can be implemented within tight schedules.

The project demonstrates how Global Hydro’s expertise in design, manufacturing, logistics and project execution can be combined to deliver complex projects safely, on time and with high performance. It shows that hydropower still offers substantial potential for innovation when site specific challenges are addressed with a holistic engineering approach.

Turning complex requirements into smart solutions.

Innovative hydropower projects often face tough conditions: ambitious goals, complex site constraints, tight schedules and pressure to reduce costs. These challenges came together in this project along with the customer’s vision for a completely new turbine design. By combining technical excellence with smart project strategies, we help our clients meet demanding requirements without compromising on performance or budget.

A world-first
turbine concept.

Global Hydro developed and implemented a completely new turbine solution - a world-first in hydropower engineering. By rethinking established principles, our team created a unique concept that combines proven technologies in a novel configuration, tailored precisely to the site’s challenges. The result: higher efficiency, simplified civil structures and greater operational flexibility.

More value through innovation.

With Stegenwald, we prove that technological innovation pays off: The new turbine concept delivers measurably higher efficiency and allows for significant cost reductions on the civil works side by simplifying the plant layout. For investors, plant owners and operators, this means: lower investment risk, reduced construction complexity and higher long-term returns.

Partner with the innovator in modern hydropower.

When it comes to pioneering turbine concepts, Global Hydro leads the way. We turn complex site challenges into smart, cost-efficient solutions and support our clients every step of the way. From first idea to commissioning, we’re your strongest partner for innovation that delivers real value.

Contact Person

Thierry Burckhart

Director Revitalization

+1 (970) 710 1285

Contact

Curious about more?