GLOBAL Hydro - News of the expansion of our premises

15.09.2017

In July we launched the expansion with the demolition of the old buildings.
Right afterwards the works for the foundation where startet. We needed to drill more than 200 holes with 13m into the ground to build our new buildings on a strong footing.
Directly following this steps the build up for the building for the electical supply has begun.
At the beginning of October all the foundations should be prepared to start with the build up of the actual buildings.

At the same time the works for our new 5-axis machining center have started. After the concrete foundation has been finished the machine was delivered in week 33. This week we already started with the installation of the new machining center.